Last July, an Interstate Bridge Replacement Program Subcommittee voted to recommend toll rate scenarios to WSTC as well as the Oregon Transportation Commissions
TJ Martinell
The Center Square Washington
The Washington State Transportation Commission has voted in support of a one-year delay to tolling on the Interstate 5 Bridge spanning the Columbia River from Vancouver to Portland, Ore., although once implemented the rates would increase faster.
Last July, an Interstate Bridge Replacement Program Subcommittee voted to recommend toll rate scenarios to WSTC as well as the Oregon Transportation Commissions. A month later, program officials anticipated a year delay for the new bridge’s timeline due to planning delays. Project officials are still working on the draft Environmental Impact Statement. Though initially planned to start in spring 2026, the subcommittee in May advocated that implementation be delayed until spring 2027. According to Program Administrator Greg Johnson, the subcommittee is seeking a Record of Decision in 2026, in which the federal government approves the project for construction.
Under the option approved by WSTC, the toll rates will escalate by 3.25% in the second and third year of tolling, rather than 2.15% as initially planned. After the third year, the toll rate increases will go back to 2.15%.
The tolling rate scenarios under consideration by the joint commissions depend on various factors, such as whether or not the new bridge has been completed, what day of the week and what time of day. Under all four scenarios, there would be a low-income program to cover 50% of the toll, though under some scenarios that program would start “once practical” as opposed to when the new bridge opens. The highest potential toll rate under the four scenarios would be $4.70, which would take effect after the new bridge is completed.
During this year’s session, the Washington State Legislature passed House Bill 1958 sponsored by House Transportation Chair Jake Fey, D-Seattle, which authorizes up to $2.5 billion in bonding to be paid for by tolling revenue.
The state Departments of Transportation for Washington and Oregon recently sought traveler feedback on what modes they use when crossing the existing I-5 Bridge. The project previously received 600 comments related to tolling and around 1,300 comments concerning the bridge’s design.
The updated tolling start date has not yet been approved by the Oregon Transportation Commission.
This report was first published by The Center Square Washington.
- Goodbye, bumpy ride on I-5 in VancouverThree coordinated WSDOT projects will improve more than 6 miles of I-5 in Clark County, backed by a $25 million investment.
- Nighttime work on I-5 between Ridgefield and Woodland will replace damaged concrete panels Sept. 14-19Granite Construction will close right and center lanes nightly on I-5 between mileposts 9.5 and 21.5 through Sept. 19.
- County seeks volunteers to serve on the Bicycle and Pedestrian Advisory CommitteeClark County seeks two volunteers, including one youth member, for its Bicycle and Pedestrian Advisory Committee; deadline is Oct. 11, 2026.
- Washington Rep. John Ley warns ballooning bridge budget needs reality checkRep. John Ley says the IBR ballooned from a $44M contract to a $13B–$15B project, with phase one still $2.2B short.
- POLL: The IBR project is described as only 30% designed and 30% funded after more than six years of work. How confident are you in the current management of the IBR program?IBR’s cost has climbed from $3.2–$4.8B to $15.2B while the project remains 30% designed and 30% funded.