40 Vancouver single family homes in IBR crosshairs plus 35 floating homes on Hayden Island

Draft Supplemental Environmental Impact Statement delayed for 4th time

John Ley 
for Clark County Today

A portion of the Draft Supplemental Environmental Impact Statement (DSEIS) for the Interstate Bridge Replacement (IBR) Program has been revealed, not by the program but due to a Public Records Request made by the Just Crossing Alliance (JCA). The program appears to be concerned that the revelation of the information will trigger a “negative public reaction,” and “hinder the decision-making process,” reports Joe Cortright.

Less than a week later it was announced the publication of the DSEIS has been delayed until much later this year. IBR critic Bob Ortblad notes this is the fourth time it has been delayed. “The IBR has no credibility,” he said. “The Federal Agencies are not buying IBR’s freeway expansion, dangerous bridge, and environmental disaster.”

The JCA-released documents are 694 pages, but not the complete DSEIS. Among missing documents are specific addresses of properties impacted that the LPA would require eminent domain process to acquire. There are 36 single-family residences, 22 retail or services businesses and one office displaced. Maps show their locations.

This map shows property impacts in Vancouver, Hayden Island, north Portland and Gresham, due to the proposed Interstate Bridge Replacement proposal. Graphic courtesy IBR
This map shows property impacts in Vancouver, Hayden Island, north Portland and Gresham, due to the proposed Interstate Bridge Replacement proposal. Graphic courtesy IBR

In Vancouver, there are seven single-family homes and 10 office, professional businesses to be taken. The houses appear to be on the west side of I-5, south of 38th Street. One IBR option would shift the bridge alignment west. If that were done, then an additional 33 multifamily residential units and three retail businesses would be taken in property acquisitions.  

On Hayden Island, “up to 35 floating homes in North Portland Harbor would be displaced by the Modified LPA. Floating homes would be treated as personal property and would be relocated to moorages within the area if available.” Additionally, 14 Hayden Island businesses would be displaced, plus an unspecified number of “marine businesses” on the south side of the north Portland harbor.

The report notes “(d)aily traffic demand over the I–5 crossing Interstate Bridge is projected to increase by more than 35 percent during the next 20 years, with stop–and–go conditions increasing to approximately 15 hours daily if no improvements are made.” It further adds: “(t)he hours of congestion and delay refers to the total number of hours that the corridor experiences congestion. Congestion on a highway occurs when average speeds are below 35 miles per hour.” There is no explanation as to why they are replacing an over congested three-lane bridge with another three-lane bridge.

Freight volumes are projected to more than double over the next 25 years. “Vehicle-hours of delay on truck routes in the Portland/Vancouver area are projected to increase by more than 90 percent over the next 20 years,” they report. “Growing demand and congestion will result in increasing delay, costs and uncertainty for all businesses that rely on this corridor for freight movement.”

The IBR program’s April newsletter says the following about the DSEIS and the process. “This comprehensive and careful review is intended to ensure the accuracy of the Draft SEIS and enable the public to provide comment on the correct information during the public comment period.”

Program Administrator Greg Johnson told community leaders “time is money” as he pushed to keep a host of committees and oversight organizations on track. He recently put a dollar figure out – $300 million for each year the project is delayed. Will the delay in releasing the DSEIS add $300 million to the cost of the project?

The plan reveals that 43 single-family residences and 35 commercial businesses will be taken by the project, including the five-year-old Hurley Building. Hayden Island would supposedly experience both “positive and negative changes.” Two public facilities would be impacted as well.

The 694 pages within the documents show the following, dated April 2023.

Parcels that would require acquisition:

  • 45 full
  • 131 partial/subsurface

Land uses that would be displaced:

  • 43 single-family residences
  • 35 commercial businesses
  • 2 public facilities
These homes along the west side of I-5 just south of the 38th Street will be impacted by the proposed Interstate Bridge Replacement project. It appears that 7 single family homes will be taken if the project is approved. One option for a western location for the bridge would claim an additional 33 residences in a multifamily unit in downtown Vancouver. Graphic courtesy IBR

These homes along the west side of I-5 just south of the 38th Street will be impacted by the proposed Interstate Bridge Replacement project. It appears that 7 single family homes will be taken if the project is approved. One option for a western location for the bridge would claim an additional 33 residences in a multifamily unit in downtown Vancouver. Graphic courtesy IBR

Additionally, the following public property will be required as part of their Locally Preferred Alternative (LPA). (Numbers in square feet).

  • Old Apple Tree Park – 3,480
  • Fort Vancouver National Historic Reserve – 40,984
  • Fort Vancouver National Historic Site – 18,255
  • Columbia River Renaissance Trail – 1,007
  • Lewis & Clark National Historic Trail – 173
  • Lower Columbia River Water Trail – 173
  • Discovery Historic Loop Trail – 2,759

There would be “temporary disturbances” of more than double the Ft. Vancouver Historic lands (above) and the other sites, during construction. “Hayden Island would experience both positive and negative changes to neighborhood cohesion including negative impacts from visual changes (larger scale than existing bridge) and residential and business displacements, as well as benefits from changes to access and circulation.”

While the project is supposed to be about the “5-mile bridge influence area,” the DSEIS shows the acquisition of property in Gresham. TriMet’s Ruby Junction maintenance facility will apparently be expanded by the IBR, with seven properties acquired in full or in part. Why is an expansion of a maintenance facility required for a three-mile extension of an existing MAX line? 

Once again, this same facility was included in the failed Columbia River Crossing (CRC) and was viewed skeptically. In the CRC, TriMet demanded 19 new MAX light rail vehicles. The IBR appears to be seeking the same number now. In contrast, TriMet only bought 4 new light rail vehicles for its current 10-mile “Better Red” extension into Hillsboro. 

The original release of the DSEIS was supposed to be in 2023. 

The beginning of these setbacks appears to have begun when the US Coast Guard demanded the project consider a movable lift span. This followed the public comment period on the IBR’s request to build a bridge offering only 116 feet of clearance for maritime vessels on the Columbia River. The Coast Guard asked for at least the current 178 feet of clearance and preferred “unlimited” clearance that would be offered either by a tunnel or a bascule bridge.

In the failed Columbia River Crossing, the plan was to “mitigate” three up-river firms, paying them $86.4 million. Today, there are at least four firms claiming harm. The program has required them to sign non-disclosure agreements. In December, the IBR’s Ray Maybe told the 16 legislators of the Bi-state Bridge Committee that they expected to have those mitigation agreements wrapped up by the end of the first quarter.  

One might wonder if the delay in the DSEIS is in part because the project has been unable to reach agreement with all the firms requiring mitigation. Alternatively, might the delay be due to the Coast Guard’s unwillingness to accept a “bridge too low?”

The IBR’s proposed project would claim 35 floating homes and 14 other businesses on Hayden Island. Graphic courtesy IBR
The IBR’s proposed project would claim 35 floating homes and 14 other businesses on Hayden Island. Graphic courtesy IBR

In December, Johnson told the 16 members of the Bi-state Bridge Committee of Washington and Oregon legislators that the cost of the project would be adjusted upward, again. The current time frame for releasing the new numbers was supposedly this summer. Cortright predicted the current $5 to $7.5 billion price tag would increase 20 percent to $9 billion. Could there be an additional delay in getting updated cost information, as a contributing factor impacting the DSEIS? 

The size of the bridge itself would increase by 38 percent on one option and 49 percent on another option. The Modified LPA is a double-deck bridge that would have 455,550 square feet of deck space, corresponding to the 38 percent increase. The other two single-deck options would have 491,180 square feet. 

All proposals only have three through lanes for vehicle traffic, plus an auxiliary lane for merging and weaving at on/off ramps. C-TRAN would be allowed to run Bus on Shoulder (BOS) on its Express bus service into Portland. This would be in addition to the inclusion of MAX light rail. 

The program shared the following with Clark County Today. The goal remains to begin early construction activities in late 2025/early 2026.

“The Interstate Bridge Replacement program has been working toward the goal of publishing the Draft Supplemental Environmental Impact Statement this spring. With technical review still underway, we no longer expect that timeframe to be feasible, and are working with our federal partners to identify the anticipated timing of the publication later this year. 

“It is not unusual for complex mega projects like the IBR program to experience a shift in the timeline.”

There are many more details to be ferreted out. Citizens will be given only 60 days to make public comments once the DSEIS is published. The more they learn now, the more informed their input will be once the final details are formally released.


Also read:

12 Comments

  1. Erin Slaughter

    What about Providence Academy!! It appears it would be in the crosshairs of this project!! Can we please try to preserve what little history Vancouver has left??

    Reply
  2. Sam Churchill

    As a resident of Hayden Island, I believe your reporting on IBR (and it’s critics) have been pivotal. Clark County Today is providing a voice of reason. No amount of money can fix this embarrassment. Thank you for keeping the public informed. Future generations will note the key role the newspaper has played.

    Reply
  3. John Jenkins

    What is wrong with our community leaders in Vancouver? First off, doesn’t the word ‘Historic’ mean anything anymore? Example: How can any of our local elected officials, Vancouver City Council be ‘OK’ with the Old Apple Tree just going away. What about the ‘Historic’ significance of Fort Vancouver? Come on people….it is time for our local leaders to get a backbone and tell WSDOT and Oregon this is not a good plan for us? Our voters don’t want Light Rail. Vancouver and Portland residents do not want tolls. It appears to me none of the elected individuals care….and what’s worse is we do not seem to have anyone from the Conservative camp willing to be the ‘Don Benton’ we need now. The displacement of all those homes without any viable input is not right. About WSDOT, remember what happened in Battle Ground??? Need to jog your memory. When they widened 502 into Battle Ground….the ice cream, burger joint (O’Bradys) was robbed of due process at 244th and SR502….by WSDOT. If you think for a minute those 43 home owners all will be given what their property is worth….forget it. The same people are at WSDOT when the O’Brady issue came up. Back to the original question I have….why do elected officials think this is ok?

    Reply
  4. Barry

    A Bridge too far!
    The voters don’t want MAX at a $2 billion price tag!
    The voters don’t want tolls!
    This is more of a career opportunity for politicians – CRC 10 years ago, IBR today, 10 years from now (when these planners retire) it’ll be called ???.
    We get the career leaders we vote for!

    Reply
  5. Margaret

    “The IBR program’s April newsletter says the following about the DSEIS and the process. “This comprehensive and careful review is intended to ensure the accuracy of the Draft SEIS and enable the public to provide comment on the correct information during the public comment period.” ‘

    When this project was labeled the CRC 10 years ago, there were errors in the data.
    Instead of using updated information on the number of people using public transit to cross the Columbia River on public buses, the IBR started by recycling the old stale data from the CRC era.
    However, public transit use across the Columbia River has declined over the last 10 years, yet the IBR data doesn’t reflect transit ridership declines, probably because updated data would show that light rail is not needed. Furthermore, the predictions of dramatic future public transit ridership increases by 2035 made during the CRC boondoggle have not materialized as forecast. Public transit ridership across the river is lower today than it was in the CRC era!
    The similar dramatic ridership increases projected by IBR today do not seem to be based on updated ridership data at all. Recycled CRC data, that isn’t accurate today seems to be the basis for the IBR rosy transit ridership predictions similar to the inflated CRC transit ridership forecasts which are being used to push gold plated light rail on an I-5 replacement bridge.
    Based on the statement in the IBR April newsletter above, is it up to the public to correct faulty IBR data produced with $MILLIONS of taxpayer dollars?

    When Clark County Today reached out to the Southwest Washington Regional Transportation Council (RTC), the data about transit ridership and the data requested wasn’t readily available. The mysterious “travel demand model” used by RTC and METRO seems to consistently produce inflated future transit demand data.
    See When the ‘facts’ don’t jive with the data on the Interstate Bridge Replacement

    Reply
  6. DONALD LEE TAYLOR

    Another 3 lane bridge?? Give me a break! It looks to me like they are just making driving in a Car more miserable with the projected up-coming increase in traffic and hyper urbanization that’s projected. Let’s just force everyone we can to take public transit… that will teach em’! That’s what they want!
    And how about the historic sites? The trails? the discovery trail goes right by my home!
    and just as Margeret has said right below me, there is hardly a reason for light rail. I just heard today on Lars Larson that the money that is expended on Tri-Met in relation to the people who ride is way out of balance. “It would knock your socks off” direct quote. Now they are wanting a “Bus only “right of way to be able to go through intersections on a red light- meaning those of us who drive will have to wait for those who are riding the Bus. In other words-“Those who pay taxes will have to wait for those who don’t.” Another Larson quote…

    I know that especially here in the Couv’ people have become very aggressive in their driving to try and get by these “Vine” rolling “Trains” that are constantly blocking traffic. What was wrong with the old Buse’s? I rode them a time or two… Every time I look at one of these Vine Trains on wheels now there’s hardly anyone on them!

    Reply
  7. Ron

    The only thing a new bridge will accomplish is no bridge lifts and maybe no total lane closers while cleaning up a wreck. It will not help traffic movement

    Reply
    1. Joy

      Well Im one of the renters of one of these houses! We have lived in this house for 10 years and I dont know what we will do if we have to move! We have kids and we cant afford to move nor do ww want to but I guess that doesnt matter😪

      Reply

Leave a Reply

Your email address will not be published. Required fields are marked *